| Detailed Estimate for the Construction of Dormitay Block at Isai Ambalam School, Auroville. | 20.07.04 | |||||||
| Description of work | Nos | Length | Breadth | Depth | Quantity | Unit | Rate | Amount |
| Site cleaning,tree cutting,marking and top soil removing | 1x1 | 15.18 | 7.5 | 113.85 | sq.m | 13 | 1480.05 | |
| Earth work excavation for foundation | ||||||||
| Main walls alround - (14.95+5.23*4+4.73*2+1.73*4+3.23*2) | 1x1 | 58.71 | 0.70 | 0.90 | 36.99 | |||
| at Verandah - (2*2+15.18)= 19.18m | 1x1 | 19.18 | 0.60 | 0.60 | 6.90 | |||
| for front side step - | 1x1 | 5.26 | 0.70 | 0.30 | 1.10 | |||
| 45.00 | cu.m | 70 | 3149.769 | |||||
| Sand filling in foundation | ||||||||
| Main walls alround - (14.95+5.23*4+4.73*2+1.73*4+3.23*2) | 1x1 | 58.71 | 0.70 | 0.05 | 2.05 | |||
| at Verandah - (2*2+15.18)= 19.18m | 1x1 | 19.18 | 0.60 | 0.05 | 0.58 | |||
| for front side step - | 1x1 | 5.26 | 0.70 | 0.05 | 0.18 | |||
| 2.81 | cu.m | 350 | 985.0225 | |||||
| Providing foundation p.c.c 1:5:10 | ||||||||
| Main walls alround - (14.95+5.23*4+4.73*2+1.73*4+3.23*2) | 1x1 | 58.71 | 0.70 | 0.10 | 4.11 | |||
| at Verandah - (2*2+14.95)= 19.18m | 1x1 | 19.18 | 0.60 | 0.10 | 1.15 | |||
| for front side step - | 1x1 | 5.26 | 0.70 | 0.10 | 0.37 | |||
| 5.63 | cu.m | 2100 | 11820.27 | |||||
| Providing foundation brick work with cement mortar 1:5 | ||||||||
| 1x1 | 58.71 | 0.56 | 0.15 | 4.93 | ||||
| 1x1 | 58.71 | 0.45 | 0.15 | 3.96 | ||||
| 1x1 | 58.71 | 0.34 | 0.20 | 3.99 | ||||
| 1x1 | 19.18 | 0.45 | 0.15 | 1.29 | ||||
| 1x1 | 19.18 | 0.34 | 0.20 | 1.30 | ||||
| steps brick work | 1x1 | 5.26 | 0.7 | 0.15 | 0.55 | |||
| 1x1 | 5.26 | 0.4 | 0.15 | 0.32 | ||||
| 16.35 | cu.m | 1550 | 25348.134 | |||||
| Providing brick shuttering for plinth beam | 1x2 | 58.71 | 0.25 | 29.355 | ||||
| 1x2 | 19.18 | 0.15 | 5.754 | |||||
| 35.109 | sq.m | 200 | 7021.8 | |||||
| Providing r.c.c 1:2:4 for plinth beam | ||||||||
| Main walls | 1x1 | 58.71 | 0.23 | 0.23 | 3.106 | |||
| at verandah | 1x1 | 19.18 | 0.23 | 0.15 | 0.662 | |||
| 3.767 | cu.m | 4500 | 16953.611 | |||||
| Providing brick work upto floor level with c.m 1:5 | 1x1 | 58.71 | 0.23 | 0.45 | 6.076 | |||
| 1x1 | 19.18 | 0.23 | 0.50 | 2.206 | ||||
| 8.282 | cu.m | 1550 | 12837.387 | |||||
| Refilling of excavated earth into the pit | 19.247 | cu.m | 35 | 673.641 | ||||
| Providing and laying d.p.c with c.m 1:2 at alround the main wall | 1x1 | 58.71 | 0.23 | 13.503 | sq.m | 140 | 1890.462 | |
| Providing exposed brick work in superstructure with c.m 1:6 | 1x1 | 50.75 | 0.23 | 2.75 | 32.099 | |||
| 1x2 | 4.96 | 0.23 | 2.55 | 5.818 | ||||
| for front side pillars | 1x4 | 0.23 | 0.23 | 2.30 | 0.487 | |||
| verandah bench brick work | 1x2 | 6.51 | 0.23 | 0.45 | 1.348 | |||
| deductions for openinngs | ||||||||
| w1 | 1x2 | 1.00 | 0.23 | 2.10 | -0.97 | |||
| w2 | 1x8 | 0.75 | 0.23 | 1.35 | -1.86 | |||
| w3 | 1x2 | 0.75 | 0.23 | 0.60 | -0.21 | |||
| opening at entrance | 1x2 | 1.00 | 0.23 | 2.10 | -0.97 | |||
| D1 | 1x2 | 1.00 | 0.23 | 2.10 | -0.97 | |||
| 34.784 | cu.m | 1650 | 57393.113 | |||||
| Providing 4.5"tk brick work at toilet | 1x2 | 1.73 | 2.75 | 9.515 | ||||
| deductions for openings | 1x2 | 0.75 | 2.1 | -3.15 | ||||
| 6.365 | sq.m | 350 | 2227.75 | |||||
| Providing r.c.c 1:2:4 for lintels and sunshade | ||||||||
| w1 | 1x2 | 1.46 | 0.23 | 0.23 | 0.15 | |||
| w2 | 1x8 | 1.21 | 0.23 | 0.23 | 0.51 | |||
| w3 | 1x2 | 1.21 | 0.23 | 0.23 | 0.13 | |||
| D1 | 1x2 | 1.46 | 0.23 | 0.23 | 0.15 | |||
| sunshade -w1 | 1x2 | 1.46 | 0.60 | 0.07 | 0.12 | |||
| sunshade -w2 | 1x2 | 2.85 | 0.6 | 0.07 | 0.24 | |||
| Front side pillar from plinth beam | 1x4 | 0.15 | 0.15 | 2.80 | 0.25 | |||
| 1.563 | cu.m | 4700 | 7346.41 | |||||
| Earth filling in flooring | ||||||||
| Men's & women's dormitory | 1x2 | 4.50 | 5.00 | 0.35 | 15.75 | |||
| Men's & women's toilet | 1x2 | 3.00 | 1.50 | 0.35 | 3.15 | |||
| under staircase | 1x1 | 1.80 | 3.46 | 0.35 | 4.36 | |||
| covered verandah | 1x1 | 14.95 | 1.77 | 0.35 | 9.26 | |||
| Foyer | 1x1 | 5.26 | 2.00 | 0.35 | 3.68 | |||
| 36.203 | cu.m | 250 | 9050.7813 | |||||
| Sand filling in flooring | ||||||||
| Men's & women's dormitory | 1x2 | 4.50 | 5.00 | 0.07 | 3.15 | |||
| Men's & women's toilet | 1x2 | 3.00 | 1.50 | 0.07 | 0.63 | |||
| under staircase | 1x1 | 1.80 | 3.46 | 0.07 | 0.87 | |||
| covered verandah | 1x1 | 14.95 | 1.77 | 0.07 | 1.85 | |||
| Foyer | 1x1 | 5.26 | 2.00 | 0.07 | 0.74 | |||
| 7.241 | cu.m | 350 | 2534.2188 | |||||
| Providing flooring p.c.c 1:4:8 | 1x2 | 4.50 | 5.00 | 0.1 | 4.50 | |||
| 1x2 | 3.00 | 1.50 | 0.1 | 0.90 | ||||
| 1x1 | 1.80 | 3.46 | 0.1 | 1.25 | ||||
| 1x1 | 14.95 | 1.77 | 0.1 | 2.65 | ||||
| 1x1 | 5.26 | 2.00 | 0.1 | 1.05 | ||||
| 10.344 | cu.m | 2000 | 20687.5 | |||||
| Providing r.c.c 1:1.5:3 for roof slab | 1x1 | 5.46 | 15.18 | 0.11 | 9.117 | |||
| roof beam | 1x1 | 5.86 | 0.23 | 0.30 | 0.404 | |||
| 1x1 | 39.84 | 0.23 | 0.15 | 1.374 | ||||
| beam connecting front side pillars | 1x1 | 15.18 | 0.23 | 0.25 | 0.873 | |||
| deductions for staircase opening | 1x1 | 3.46 | 1.80 | 0.12 | -0.747 | |||
| 11.021 | cu.m | 5500 | 60617.799 | |||||
| Providing and laying tiles roof at verandah | 1x1 | 15.18 | 2.73 | 41.44 | sq.m | 475 | 19684.665 | |
| Plastering of inner walls with cement mortar 1:4 | 1x2 | 19.00 | 2.74 | 104.12 | ||||
| 1x2 | 6.77 | 2.74 | 37.10 | |||||
| 1x2 | 5.00 | 2.74 | 27.40 | |||||
| staircase walls | 1x2 | 3.46 | 3.60 | 24.91 | ||||
| 1x1 | 1.80 | 3.60 | 6.48 | |||||
| window side | 1x8 | 4.20 | 0.23 | 7.73 | ||||
| w3 | 1x2 | 2.70 | 0.23 | 1.24 | ||||
| door side | 1x8 | 6.20 | 0.23 | 11.41 | ||||
| Deductions for openings w2 | 1x8 | 0.75 | 1.35 | -8.10 | ||||
| opening at entrance | 1x2 | 1.00 | 2.10 | -4.20 | ||||
| w1 | 1x2 | 1.00 | 2.10 | -4.20 | ||||
| D2 | 1x2 | 0.75 | 2.1 | -3.15 | ||||
| D1 | 1x2 | 1.00 | 2.1 | -4.20 | ||||
| w3 | 1x2 | 0.75 | 0.6 | -0.90 | ||||
| 195.640 | sq.m | 100 | 19563.96 | |||||
| Pointing of outer walls with cement mortar 1:3 | 1x1 | 43.5 | 4.20 | 182.7 | ||||
| veranda bench brick work | 1x2 | 6.51 | 0.45 | 5.86 | ||||
| Deduction for openings | 1x8 | 0.75 | 1.35 | -8.10 | ||||
| w1 | 1x2 | 1.00 | 2.10 | -4.20 | ||||
| 176.259 | sq.m | 50 | 8812.95 | |||||
| Sunshade top plastering with cement mortar | 1x2 | 1.56 | 0.6 | 1.872 | ||||
| 1x2 | 2.93 | 0.6 | 3.516 | |||||
| 5.388 | sq.m | 100 | 538.8 | |||||
| Terrocotta colour floor finishing with white cement mortar 1:4 | ||||||||
| Men's & women's dormitory | 1x2 | 4.50 | 5.00 | 45.00 | ||||
| Men's & women's toilet | 1x2 | 3.00 | 1.50 | 9.00 | ||||
| under staircase | 1x1 | 1.80 | 3.46 | 6.23 | ||||
| covered verandah | 1x1 | 14.95 | 1.77 | 26.46 | ||||
| Foyer | 1x1 | 5.26 | 2.00 | 10.52 | ||||
| front steps | 1x1 | 0.80 | 5.26 | 4.21 | ||||
| door bottom | 1x8 | 1.00 | 0.23 | 1.84 | ||||
| 103.258 | sq.m | 135 | 13939.763 | |||||
| Providing and simple grill windows with mesh | ||||||||
| w1 | 1x2 | 1 | 2.1 | 4.20 | ||||
| w2 | 1x8 | 0.75 | 1.35 | 8.10 | ||||
| w3 | 1x2 | 0.75 | 0.6 | 0.90 | ||||
| 13.20 | sq.m | 800 | 10560.00 | |||||
| Painting of grill windows | ||||||||
| w1 | 2x2 | 1 | 2.1 | 8.40 | ||||
| w2 | 2x8 | 0.75 | 1.35 | 16.20 | ||||
| w3 | 2x2 | 0.75 | 0.6 | 1.80 | ||||
| 26.40 | sq.m | 80 | 2112.00 | |||||
| Providing and fixing ready made flush doors | ||||||||
| D1 | 1x2 | 1.00 | 2.10 | 4.20 | ||||
| D2 | 1x2 | 0.75 | 2.10 | 3.15 | ||||
| 7.35 | sq.m | 1300 | 9555.00 | |||||
| Painting of doors | ||||||||
| D1 | 2x2 | 1.00 | 2.10 | 8.40 | ||||
| D2 | 2x2 | 0.75 | 2.10 | 6.30 | ||||
| 14.70 | sq.m | 120 | 1764.00 | |||||
| Construction of Staircase: | ||||||||
| Providing and fixing precast staircase steps | 14 | 14.00 | nos | 700 | 9800.00 | |||
| landing slab | 1 | 2.26 | 1.36 | 0.07 | 0.215 | cu.m | 5500 | 1183.34 |
| Providing and fixing staircase hand rail | 1x1 | 5.00 | 0.75 | 5.00 | rmt | 650.00 | 3250.00 | |
| Providing and laying cuddapha stone on front side bench | 1x1 | 6.51 | 0.45 | 2.93 | sq.m | 261.5 | 765.95 | |
| Providing and fixing white colour wash basin | 1x2 | 2 | nos | 450 | 900.00 | |||
| Providing and fixing wash basin tap | 1x2 | 2 | nos | 350 | 700.00 | |||
| Providing and fixing E.w.c at toilet | 1x2 | 2 | nos | 550 | 1100.00 | |||
| Providing and fixing tap at toilet | 1x2 | 2 | nos | 300 | 600.00 | |||
| Providing and fixing ordinary shower | 1x2 | 2 | nos | 450 | 900.00 | |||
| Internal plumbing work | lumpsum | 5000.00 | ||||||
| Internal Electrical work | 15 | 15 | pts | 650 | 9750.00 | |||
| Septic tank | lumpsum | 10000.00 | ||||||
| Terrace work: | ||||||||
| Providing parapet wall with c.m 1:6 | 2x4 | 4.23 | 0.23 | 0.75 | 5.84 | cu.m | 1650 | 9631.71 |
| Providing weathering course | 1x1 | 14.72 | 5.00 | 0.075 | 5.52 | |||
| deductions for openings | 1x1 | 2.10 | 3.46 | 0.075 | -0.54 | |||
| 4.98 | cu.m | 1300 | 6467.565 | |||||
| Providing and laying ferrocement seating slab | 1x4 | 2.96 | 0.45 | 5.328 | ||||
| 1x2 | 1.46 | 0.45 | 1.314 | |||||
| 6.642 | sq.m | 250 | 1660.50 | |||||
| Plastering of inner parapet walls | 2x4 | 4.23 | 0.85 | 28.76 | sq.m | 100 | 2876.40 | |
| Terrace floor finishing with cement mortar | 1x1 | 14.72 | 5.00 | 73.60 | ||||
| deductions for openings | 1x1 | 2.10 | 3.46 | -7.266 | ||||
| 66.334 | sq.m | 100 | 6633.40 | |||||
| Total Estimated Amount of Building : | 399767.71 | |||||||
| Lotus Pond | ||||||||
| Earth work excavation for walls | 1 | 5.56 | 0.3 | 0.3 | 0.50 | cu.m | 65 | 32.526 |
| Sand filling in foundation | 1 | 5.56 | 0.3 | 0.1 | 0.17 | cu.m | 300 | 50.04 |
| Providing foundation p.c.c | 1 | 5.56 | 0.3 | 0.1 | 0.17 | cu.m | 1700 | 283.56 |
| Providing brick work | 1 | 5.56 | 0.23 | 0.75 | 0.96 | cu.m | 1650 | 1582.5 |
| Mesh Plastering of inner wall and flooring with cement mortar | 1 | 1.8 | 0.75 | 1.35 | ||||
| 1 | 5.56 | 0.5 | 2.78 | |||||
| 4.13 | sq.m | 150 | 619.5 | |||||
| 2568.14 | ||||||||
| Gross Amount: | 402335.86 | |||||||