Odanadi Building Expenses for the duration April 2004-March 2005 |
||||||
|
For the new Residential Home "MADILU" |
||||||
|
Posted August 13, 2005 |
||||||
|
Rs. |
||||||
|
1. Labour payment |
66492 |
|||||
|
(building construction) |
||||||
|
2. Labour payment -- Carpentary work |
53590 |
|||||
|
3. Labour payment - Painting |
35000 |
|||||
|
4. Labour payment - floor and roof tiles laying |
67512 |
|||||
|
5. Cinders |
3276 |
|||||
|
6. Cement |
112295 |
|||||
|
(770 bags) |
||||||
|
7. Sand |
41500 |
|||||
|
(14 load sand and boulders 1 load) |
||||||
|
8. Bricks |
8000 |
|||||
|
(4000 bricks) |
||||||
|
9. Contractor labour payment |
104400 |
|||||
|
(paid to Mr. Mahadev and Mr. Shivanna) |
||||||
|
10. Centring materials rent |
10000 |
|||||
|
11. Electricty items |
161659 |
|||||
|
12. Electricity charges |
17849 |
|||||
|
13. Labour payment - electricity |
15000 |
|||||
|
14. Labour payment - plumbing |
7000 |
|||||
|
15. Bath room fittings |
98844 |
|||||
|
(taps and pipes) |
||||||
|
16. Wash bain and camodes |
123792 |
|||||
|
17. Pipes |
11193 |
|||||
|
18. Door and window fittings |
54500 |
|||||
|
19. Timber |
50000 |
|||||
|
20. Tiles powder |
5670 |
|||||
|
21. Plumbing items |
84981 |
|||||
|
22. Floor tiles, wall tiles, border tiles |
485291 |
|||||
|
23. Slabs purchased |
27681 |
|||||
|
24. Paint purchased |
96674 |
|||||
|
25. Rent for painters home |
1800 |
|||||
|
26. Window glass purchased |
25765 |
|||||
|
27. Roof tiles |
54852 |
|||||
|
28. Plumbing items purchased |
31263 |
|||||
|
29. Poles |
2492 |
|||||
|
30. Wood plaining charges |
10870 |
|||||
|
31. cart rent, auto chages and transportation charges |
5550 |
|||||
|
32. Miscellaneous |
24781.5 |
|||||
|
(channel plates, rope, neils, plastic sheet, |
||||||
|
lime paste, white cement, handles, ladder, |
||||||
|
chamber plates, centring materials rent etc.) |
||||||
|
Total |
1,899,572.50 |
|||||